Advanced Product Quality Planning (APQP)

When to use

Use this skill when:

  • A new product or part is being launched and a structured quality plan is needed
  • Managing an APQP project and tracking deliverables across phases
  • Conducting an APQP gate review to assess launch readiness
  • A customer requests an APQP status report or phase completion confirmation
  • Auditing whether a supplier's APQP process is adequate

Prerequisites

  • Customer requirements, specifications, and drawings (or RFQ package)
  • Programme timing (SOP date, PPAP submission date, prototype gates)
  • Nominated APQP team (cross-functional: engineering, quality, purchasing, manufacturing, logistics)
  • Customer APQP template if OEM-specific format required

Workflow

Overview — The 5 APQP Phases

Phase 1          Phase 2          Phase 3          Phase 4          Phase 5
Plan & Define → Product Design → Process Design → Product & Process → Feedback &
                & Development   & Development      Validation         Corrective Action
     ↓               ↓               ↓                ↓                  ↓
  Program         Prototype       Pre-launch         PPAP              SOP +
  approval         build           build           submission          Production

All phases run with concurrent engineering — phases overlap and teams work in parallel.


Phase 1 — Plan and Define Program

Objective: Understand customer requirements and define what the product must do.

Key deliverables:

Deliverable Description
Voice of the Customer (VOC) Customer wants, needs, expectations — translated to measurable requirements
Design Goals Product performance targets derived from VOC
Reliability and Quality Goals Target failure rate, warranty targets, Cpk targets
Preliminary Bill of Materials Draft BOM from design intent
Preliminary Process Flow High-level process sequence
Preliminary Special Characteristics Initial list of critical/significant characteristics
Product Assurance Plan Quality plan for the programme
Management Support Signed-off programme charter with resources and timing

Gate 1 pass criteria:

  • Customer requirements documented and agreed
  • Feasibility confirmed (technical and commercial)
  • Team chartered and timing plan approved
  • Special characteristics list preliminary but complete

Phase 2 — Product Design and Development

Objective: Translate customer requirements into a product design with verified characteristics.

Key deliverables:

Deliverable Description
DFMEA Design FMEA — all failure modes analysed, H-AP items addressed
Design Verification Plan (DVP) Test plan linked to DFMEA failure modes
Drawing and Specification Release Fully released engineering drawings and 3D data
Material Specifications Raw material specs, supplier approval plan
Drawing and Specification Changes Change management process in place
New Equipment and Tooling List of new equipment/tooling required
Special Product and Process Characteristics Updated with design detail
Gauge Plan MSA requirement list — which characteristics need MSA studies
Prototype Control Plan Control plan for prototype builds
Prototype Build Prototype parts manufactured and tested
Engineering Drawings Released and approved

Gate 2 pass criteria:

  • DFMEA complete with all H-AP actions closed
  • DVP complete and test execution started
  • Prototype build results acceptable
  • All special characteristics identified and confirmed
  • No outstanding major design concerns

Phase 3 — Process Design and Development

Objective: Design and verify the manufacturing process.

Key deliverables:

Deliverable Description
Packaging Standards Packaging design, labelling, MMOG/LE if required
Product/Process Quality System Review Internal quality system audit against customer requirements
Process Flow Chart Detailed process flow for all operations
Floor Plan Layout Manufacturing floor layout approved
Characteristics Matrix Matrix linking process steps to product characteristics
PFMEA Process FMEA — all failure modes, AP ratings, H-AP actions complete
Pre-Launch Control Plan Control plan for pre-launch production
Process Instructions Work instructions for all operations
MSA Plan Gauge R&R plan for all measurement systems
Preliminary Process Capability Study Plan Plan for capability studies on special characteristics
Packaging Specifications Final packaging specs including OEM labelling

Gate 3 pass criteria:

  • PFMEA complete, H-AP actions closed or formally accepted
  • Pre-launch Control Plan approved
  • Process instructions complete for all operations
  • Tooling and equipment installed and qualified
  • No unresolved open issues blocking pre-launch build

Phase 4 — Product and Process Validation

Objective: Validate the production process and prepare for PPAP submission.

Key deliverables:

Deliverable Description
Production Trial Run Significant Production Run (minimum run to PPAP requirements)
MSA Studies Gauge R&R completed for all special characteristics
Preliminary Process Capability Cpk study on special characteristics (target ≥ 1.67)
Production Part Approval (PPAP) All 18 PPAP elements complete and submitted
Production Validation Testing Final validation tests on production parts
Packaging Evaluation Production packaging validated
Production Control Plan Final production control plan approved
Quality Planning Sign-Off Customer approval of PPAP and APQP completion
Management Support Sign-Off Internal management approval for SOP

Gate 4 pass criteria (= PPAP approval):

  • Significant production run completed (minimum 300 consecutive parts per AIAG PPAP 4th ed §4.0, unless the customer specifies otherwise in writing)
  • Dimensional results 100% conforming
  • Cpk ≥ 1.67 on all special characteristics (or customer-approved deviation)
  • %GRR < 30% for all MSA studies
  • PPAP submitted and customer approval received
  • No open concerns from validation testing

Phase 5 — Feedback, Assessment and Corrective Action

Objective: Continuous improvement after SOP — close the loop on any issues found in production.

Key activities:

Activity Description
Reduced variation Monitor process capability, reduce common-cause variation
Improved customer satisfaction Track warranty, field returns, and customer scorecards
Improved delivery and service Monitor OTD (on-time delivery) and logistics performance
Lessons learned Document lessons learned for future programmes
Control Plan updates Update based on production data and any quality escapes
PFMEA updates Update based on field failures and warranty data

Phase 5 is ongoing. There is no defined end gate — it runs for the life of the programme.


APQP timing — rule of thumb

Milestone Typical timing before SOP
Programme approval / Phase 1 complete 18–24 months
Design release / Phase 2 complete 12–15 months
Process design complete / Phase 3 complete 8–10 months
PPAP submission 4–6 months
PPAP approval (customer) 3–4 months
Pre-production builds 2–3 months
SOP 0

Automotive OEM programmes vary — always confirm with the customer's APQP coordinator.

Validation criteria

At each gate review, verify:

  • All deliverables for the phase are complete (not "in progress")
  • No open H-AP items in DFMEA or PFMEA without approved actions
  • No outstanding design or process concerns without a documented resolution plan
  • Team sign-off obtained from all functions (quality, engineering, manufacturing, purchasing)
  • Customer confirmation received before advancing to next phase

Gate reviews are STOP gates — do not advance until all criteria are met.

Common mistakes

  • Starting Phase 2 before customer requirements are fully understood and documented (Phase 1 incomplete)
  • PFMEA created after process is already running — it must drive process design, not document it
  • Production trial run shorter than 300 consecutive parts without written customer authorisation — the PPAP samples must come from this run; a shorter run requires an explicit customer waiver
  • Capability studies run on off-tool or pre-production parts — must be from production tooling
  • Prototype Control Plan used for PPAP submission — production control plan must be separate
  • MSA studies done after PPAP submission — must be complete before PSW is signed
  • Phase 5 never started — APQP is treated as "done" at SOP rather than as a continuous loop
  • Lessons learned not captured — same problems recur on next programme

Output Format

At the start of each use, ask the user:

"How would you like to receive the output? A — Structured Markdown (formatted tables and sections, ready to copy) B — Plain tables (simplified structure for Excel or Word) C — Narrative report (flowing text for a formal document or email)

Default: A."

Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.

Changelog

Version Date Author Change
1.0 2026-06-06 @RBraga01 Initial release
1.1 2026-06-06 @migmcc Added 300-part production trial run minimum to Gate 4 criteria and Common Mistakes