When to Use
- Coordinate a multi-team technical initiative with shared milestones
- Map dependencies, critical path, and integration points
- Maintain RAID log (risks, actions, issues, decisions)
- Run launch readiness or go/no-go reviews
- Produce weekly program status for leadership or steering committee
- Resolve cross-team blockers without owning the technical design
When NOT to Use
- Write BRDs, user stories, or process maps →
business-analyst - Choose canary vs blue-green or write cutover runbooks →
deployment-strategist - Implement pipelines, GitOps, or on-call →
devops - Own data platform roadmap or data governance →
data-manager - Author service RFCs or code →
senior-software-engineer,fullstack-software-engineer - Platform product roadmap for IDP →
platform-engineer - Architecture decisions, ADRs, design review →
senior-system-architecture - Strategy, business case, operating model →
business-consultant - Technical discovery, solution architecture, RFP response authoring →
solutions-architect
Related skills
| Need | Skill |
|---|---|
| Release strategy and rollback design | deployment-strategist |
| Pipeline and environment operations | devops |
| Requirements and business cases | business-analyst |
| UX scope and design handoff | product-designer |
| Engineering design and RFCs | senior-software-engineer |
| Data program roadmaps | data-manager |
| Security/compliance program gates | compliance-engineer, cybersecurity |
| System architecture and ADRs | senior-system-architecture |
| Strategy and business case | business-consultant |
| Incident ops: SEV, on-call, postmortems | incident-management-engineer |
| Board resolutions, entity, corporate closing | corporate-counsel |
| Launch and stakeholder messaging | communication-lead |
| Developer training program rollout | developer-education-lead |
| Exec/VIP and community customer escalations | community-executive-escalations-program-manager |
| Data center design and facility execution | data-center-design-execution-lead |
| Multi-site DC portfolio planning and steering | data-center-portfolio-planning-execution-lead |
| M&A diligence, signing, closing coordination | transaction-manager |
| Coordinated vulnerability disclosure program | technical-program-manager-security-cvd |
| Customer solution design and delivery handoff package | solutions-architect |
Core Workflows
1. Program charter
Define before execution:
- Objective and measurable outcomes (not output lists)
- Scope: teams, systems, in/out
- Timeline: phases, hard dates, external dependencies
- Roles: DRI per workstream, escalation path
- Success metrics and definition of done
See references/program_charter.md for charter template.
2. Work breakdown and dependencies
- Decompose into workstreams (each with one DRI)
- List deliverables per workstream with dates
- Build dependency graph (finish-to-start; flag circular deps)
- Identify critical path and buffer on that path only
- Mark integration milestones (API freeze, env parity, dress rehearsal)
See references/dependency_risk.md for dependency types and RAID format.
3. Operating rhythm
| Cadence | Audience | Purpose |
|---|---|---|
| Weekly | Workstream DRIs | Blockers, date slips, dependency asks |
| Biweekly | Sponsors / leads | Scope, risk, decision needs |
| Pre-launch | Launch council | Readiness checklist |
- One source of truth for status (doc or tracker—not duplicate spreadsheets)
- Decisions logged with owner and date; no re-litigating closed calls
See references/status_reporting.md for status template.
4. Risk and issue management
- Risk: may happen → mitigation + trigger
- Issue: happened → owner + ETA + comms plan
- Escalate when: critical path slip > agreed threshold, scope creep without sponsor, unresolved cross-team conflict
See references/dependency_risk.md for RAID columns.
5. Stakeholder communication
- Status: RAG per workstream, changes since last week, asks
- No technical deep dives in exec updates—link appendix
- Align messaging before external comms (customers, support, legal)
See references/stakeholder_comms.md for audience-specific formats.
6. Launch readiness
Gate checklist before production:
- All critical-path items complete or explicitly waived by sponsor
- Rollback/runbook owned (
deployment-strategist+devops) - Monitoring and on-call briefed
- Support/docs updated
- Go/no-go with named approvers
See references/launch_readiness.md for full checklist.
When to load references
- Charter and phases →
references/program_charter.md - Dependencies and RAID →
references/dependency_risk.md - Status and steering →
references/status_reporting.md - Exec and sponsor comms →
references/stakeholder_comms.md - Go/no-go →
references/launch_readiness.md