Planning a Sprint

Select tickets, define a goal, and commit to a sprint scope.

Quick Reference

  • Input: Prioritized backlog, team capacity, sprint duration.
  • Output: Sprint plan with selected tickets, sprint goal, capacity allocation.
  • Rule: Don't overcommit — plan for ≤80% of theoretical capacity.

HARD-GATE

DO NOT commit more than the team's historical velocity.
DO NOT select tickets with unresolved dependencies or unclear acceptance criteria.
DO set a single, clear sprint goal that every selected ticket supports.

Core Process

  1. Gather inputs — prioritized backlog (from prioritize-backlog), team capacity, sprint dates, historical velocity.
  2. Define sprint goal — every selected ticket must support this goal.
  3. Select tickets — start from the top of the backlog, stop when total estimate reaches ≤80% of capacity (see Capacity Heuristics below).
  4. Validate — check no ticket has unresolved dependencies, unclear acceptance criteria, or missing estimates. Use the Common Anti-Patterns table as a checklist.
  5. Flag — tickets that almost made the cut (next sprint), dependency risks, stretch goals.
  6. Output — sprint plan using the format in Output Style.

Capacity Heuristics

Theoretical Capacity

  • Per person per day: 6 productive hours.
  • Sprint capacity: team_size × sprint_days × 6h × utilisation_factor
  • Utilisation factor: 0.8 for stable teams; 0.6–0.7 for new or high-uncertainty teams.

Velocity

  • Rolling average: Mean completed points across last 3–5 sprints; exclude disrupted sprints.
  • No history: Use theoretical_capacity × 0.6 as a conservative baseline.
  • Declining trend: Use the most recent sprint's figure rather than the average.

Common Anti-Patterns

Anti-Pattern Mitigation
Planning to 100% capacity Cap at 80%
Including unestimated tickets Estimate before committing
Multiple sprint goals One goal per sprint
Ignoring dependencies Resolve or defer dependents
Carry-over without re-estimation Re-estimate carry-over tickets

Output Style

  1. Sprint header — name, dates, duration, team capacity.
  2. Sprint goal — single sentence.
  3. Selected tickets — | Rank | Ticket | Estimate | Confidence | Notes |
  4. Capacity allocation — total committed, buffer (%), stretch goals.
  5. Deferred — top 3 items that didn't fit, for next sprint visibility.
  6. English only unless user requests otherwise.

Worked example: assets/example-sprint-plan.md.

Integration

Skill When to chain
prioritize-backlog Use ordered backlog as input to ticket selection
estimate-tasks Reference estimates for capacity-based selection
identify-risks Scan sprint plan for dependency and capacity risks