Project Schedule Template Expert

Expert in project scheduling, WBS, timeline management, and resource allocation.

Work Breakdown Structure (WBS)

wbs_principles:
  100_percent_rule: "WBS must include 100% of project scope"
  mutual_exclusivity: "No overlapping work between elements"
  appropriate_detail: "Break down until estimable (8-80 hours)"

  numbering:
    level_1: "1.0, 2.0 (Phases)"
    level_2: "1.1, 1.2 (Deliverables)"
    level_3: "1.1.1 (Work packages)"

wbs_template:

  • id: "1.0" name: "Initiation" deliverables:

    • "1.1 Project Charter"
    • "1.2 Stakeholder Analysis"
  • id: "2.0" name: "Planning" deliverables:

    • "2.1 Project Plan"
    • "2.2 Technical Design"
  • id: "3.0" name: "Execution" deliverables:

    • "3.1 Development"
    • "3.2 Testing"
  • id: "4.0" name: "Deployment" deliverables:

    • "4.1 Production Release"
  • id: "5.0" name: "Closure" deliverables:

    • "5.1 Documentation"
    • "5.2 Lessons Learned"

## Dependencies

```yaml
dependency_types:
  finish_to_start:
    code: "FS"
    description: "Successor starts when predecessor finishes"
    most_common: true

  start_to_start:
    code: "SS"
    description: "Both start together"

  finish_to_finish:
    code: "FF"
    description: "Both finish together"

  lag_lead:
    lag: "FS+5 = Start 5 days after"
    lead: "FS-3 = Start 3 days before finish"

Duration Estimation

three_point_estimation:
  formula: "(O + 4M + P) / 6"
  definitions:
    optimistic: "Best case (10% probability)"
    most_likely: "Most probable duration"
    pessimistic: "Worst case (10% probability)"

  example:
    optimistic: 10
    most_likely: 15
    pessimistic: 26
    result: "16 days"

risk_buffers:
  low_risk: "10-15%"
  medium_risk: "20-30%"
  high_risk: "40-50%"

Resource Allocation

resource_planning:
  max_utilization: "80% recommended"
  buffer: "20% for meetings, admin, unexpected"

  capacity_formula: "Working Days × Hours/Day × Availability %"

resource_leveling:
  techniques:
    - "Delay non-critical tasks"
    - "Split tasks"
    - "Add resources"
    - "Overtime (short-term only)"

Critical Path

critical_path:
  definition: "Longest path determining minimum duration"
  characteristics:
    - "Zero total float"
    - "Delay impacts project end date"

  calculations:
    early_start: "Max(predecessor early finishes)"
    early_finish: "Early start + Duration"
    late_finish: "Min(successor late starts)"
    late_start: "Late finish - Duration"
    total_float: "Late start - Early start"

Phase Guidelines

phase_duration:
  initiation: "5-10%"
  planning: "15-25%"
  execution: "50-70%"
  closure: "5-10%"

Best practices

  1. WBS first — start with a full work breakdown
  2. Realistic estimates — use three-point estimation
  3. Buffer planning — set aside buffers for risks
  4. Critical path focus — prioritize the critical path
  5. Resource leveling — avoid overallocation
  6. Regular updates — update the schedule weekly