Change Control

Reference sources: PMBOK Change Control, Agile Change Management

Applicable scenarios

  • A product manager adds requirements on the fly during project execution
  • Output changes in upstream workflows
  • Changes in external constraints (regulations, resources, time)
  • The technical solution needs adjustment

Core principles

1. 变更必经评估
   不能"先改了再说"
   即使是"小变更"也要评估
  1. Change impact must be assessed comprehensively Not just "how much more time it takes" Also consider: risks, dependencies, impact on delivered items

  2. Change decisions must be recorded Accept/reject/defer + reason Traceable during future retrospectives

  3. Stakeholders must be notified of changes Downstream workflows that have already been handed off must receive notification


## 变更评估流程

```text
1. 接收变更请求
   ↓
2. 描述变更内容
   - 变更什么(具体到任务/功能/字段)
   - 为什么变(业务原因)
   - 紧急程度
   ↓
3. 评估影响范围
   - 影响哪些任务?
   - 影响哪些工作流?
   - 影响哪些已交付物?
   ↓
4. 评估对工期的影响
   - 增加多少工时
   - 是否影响关键路径
   - 是否需要延期
   ↓
5. 评估对风险的影响
   - 引入哪些新风险
   - 缓解原有风险
   - 风险等级变化
   ↓
6. 决策(接受/拒绝/延期)
   ↓
7. 如果接受:
   - 更新计划
   - 通知相关工作流
   - 记录决策
   ↓
8. 如果拒绝:
   - 记录原因
   - 反馈给请求方
   - 提供替代方案(如有)
   ↓
9. 如果延期:
   - 加入下期 backlog
   - 记录原因

Change classification

Micro change (M-Change)

- 范围:影响单个任务
- 工时:< 30min 增加
- 决策:项目经理可直接决定
- 流程:简化评估即可

例:
  - 调整一个错误码的文案
  - 增加一个表单的校验规则

Standard change (S-Change)

- 范围:影响 1~3 个任务
- 工时:30min ~ 2h 增加
- 决策:项目经理评估后决定
- 流程:完整评估流程

例:
  - 增加一个用户故事
  - 调整 API 字段

Major change (M+ Change)

- 范围:影响 4+ 个任务或多个工作流
- 工时:> 2h 增加
- 决策:需要产品经理 + 项目经理共同决定
- 流程:完整评估 + 风险审查 + 利益相关方确认

例:
  - 增加新功能模块
  - 重构核心流程
  - 改变技术架构

Change impact assessment template

## 变更评估:[变更标题]

### 变更基本信息

- **变更编号**:CR-001
- **请求方**:product-manager / 客户 / 外部约束
- **请求时间**:YYYY-MM-DD HH:MM
- **紧急程度**:紧急 / 高 / 中 / 低

### 变更描述

**变更内容**:
[具体到任务/功能/字段]

**变更原因**:
[业务原因或外部约束]

### 影响评估

#### 任务影响

| 任务 ID | 影响类型 | 影响描述 |
|---------|---------|---------|
| T4 | 修改 | 增加 3 个字段 |
| T5 | 新增 | 新增校验逻辑 |
| T7 | 修改 | 测试用例需要更新 |

#### 工作流影响

| 工作流 | 影响 | 需要的工作 |
|--------|------|----------|
| api-designer | 修改契约 | +15min |
| backend | 实现新字段 | +30min |
| frontend | 更新表单 | +20min |
| qa | 补充测试 | +15min |

#### 工期影响

- 总增加工时:80min
- 是否影响关键路径:是 / 否
- 整体延期:从 +160min 到 +200min

#### 风险影响

- 新增风险:
  - R6: 新字段可能与现有数据冲突
- 加剧已有风险:
  - R3 (QA 测试发现 Bug) 概率提升

### 决策

**决策**:✅ 接受 / ❌ 拒绝 / ⏰ 延期到下期

**决策人**:[项目经理 / 产品经理]

**决策理由**:
[为什么这样决策]

### 接受后的行动

- [ ] 更新 PRD
- [ ] 更新 API 契约
- [ ] 通知 backend / frontend / qa
- [ ] 调整里程碑时间点
- [ ] 更新风险清单

### 通知清单

- [ ] product-manager
- [ ] api-designer
- [ ] backend-engineer
- [ ] frontend-engineer
- [ ] qa-engineer

Change decision matrix

                价值(业务/用户)
              低    中    高
        ┌─────┬─────┬─────┐
   高   │ 拒  │ 延  │ 评估 │
成   ├─────┼─────┼─────┤
本   中 │ 拒  │ 评估│ 接受 │
        ├─────┼─────┼─────┤
   低   │ 延  │ 接受│ 接受 │
        └─────┴─────┴─────┘

成本 = 工期 + 风险 + 复杂度
价值 = 业务影响 + 用户价值 + 紧急程度

Workflow

1. 收到变更请求
   ↓
2. 分类(微/标准/重大)
   ↓
3. 评估影响(用模板)
   ↓
4. 应用决策矩阵
   ↓
5. 决策(接受/拒绝/延期)
   ↓
6. 记录决策(写入变更日志)
   ↓
7. 通知所有相关方
   ↓
8. 更新计划/PRD/API 契约等
   ↓
9. 调整后续任务的依赖关系

Quality self-check

□ 变更内容是否具体(不是"优化一下")
□ 是否评估了所有受影响的任务
□ 是否评估了所有受影响的工作流
□ 是否评估了风险变化
□ 决策是否有记录(不是口头说说)
□ 是否通知了所有相关方
□ 是否更新了已交付物(PRD/API/...)

Common pitfalls

  1. "Small changes" are not assessed— a single field change may affect 5 workflows
  2. Change assessment is not comprehensive— only looking at work hours, ignoring risks and delivered items
  3. Decisions are not recorded— later there is wrangling over "why was it changed"
  4. Notification is inadequate— downstream workflows do not know about the change and continue as before
  5. Frequently accepting changes— the project spirals out of control and is never finished
  6. Rejecting changes without explanation— loss of trust
  7. Deferred changes are not tracked— deferred forever, and finally forgotten

Supporting templates

  • templates/change-control-template.md — change request + impact assessment + change log template

Collaboration with other skills

上游:
  product-manager → 提交变更请求

平行:
  risk-management → 评估变更带来的风险
  handoff-protocol → 变更后重新交接

下游:
  wbs-decomposition → 更新任务列表
  critical-path → 重新计算关键路径
  progress-tracking → 追踪变更后的执行