Shortage Impact Map

Purpose

Deterministically explode the shortage: net the short part's usable on-hand and the incoming (late) PO against every open order that consumes it, and produce a per-order impact row (product, line, order, need-by, quantity at risk, status) plus a rolled-up impact summary (worst severity + the first-impact date). This is the mapping the whole packet turns on.

When to use

  • After supply-knowledge-retrieve, in every run.
  • "Which lines and orders does this shortage hit, and when does it bite?".

Inputs

  • The contract payload with supply{} (on_hand, on_order, safety_stock), promised_date, revised_date and retrieved.open_orders[] (contract mfg.supplier-disruption.v1).

Steps

  1. Validate the payload against the contract.
  2. Run scripts/shortage_impact_map.py --intake disruption-intake.json --out impact-map.json.
  3. Do not restate or re-derive the netting in prose; quote the engine output verbatim.
  4. Emit the {impact_map, impact_summary} contract payload and the preliminary next_best_action.

Output

Contract mfg.supplier-disruption.v1 with a populated impact_map[] (per-order status + qty at risk) and impact_summary{} (worst_severity, first_impact_date, affected products/orders, total qty at risk, below_safety_stock, confidence, source=engine:shortage_impact_map) — the {impact} hop.

Grounding requirements

The netting and per-order status cite references/impact-mapping-rules.md #3-#4; the first-impact date cites #5; the summary cites #6.

Constraints

  • All mapping logic happens in the engine. The model must never decide the impact or the dates itself.
  • The incoming (late) PO only covers orders whose need-by is on/after the revised date (impact-mapping-rules.md #2) — do not credit it earlier.
  • Never drop a late_shipment (customer order at risk) to make the picture look better — it is the reason a case is critical.

Escalation / uncertainty

  • Incomplete MRP position (missing open orders, on-hand or revised date) or a below-safety-stock projection: the engine adds to escalations[]; surface it and confirm the netting in the ERP before a mitigation is committed (impact-mapping-rules.md #7).