Submittal Intelligence Skill

Overview

The submittal-intelligence skill performs comprehensive compliance reviews of submitted product data, shop drawings, and samples against specification requirements from project intelligence. It automates the verification process by:

  • Extracting spec requirements from relevant CSI sections with testable, verifiable criteria
  • Parsing submittal documents (PDFs, data sheets, shop drawings) to extract product specifications and performance data
  • Building a compliance matrix that cross-references each specification requirement with the submitted value
  • Determining compliance status for each line item: Compliant, Non-Compliant, Partially Compliant, or Unable to Verify
  • Generating professional review comments suitable for architect/engineer review cycles
  • Producing an overall recommendation: Approved, Approved as Noted, Revise and Resubmit, or Rejected
  • Tracking submission history and flagging changes from previous revisions

The skill produces deliverables suitable for direct inclusion in RFI responses, meeting minutes, and project correspondence.

When to Use

  • Submittal PDFs uploaded for review by contractors or suppliers
  • Verifying products meet specifications before purchase or installation approval
  • Preparing review comments for architect/engineer sign-off
  • Processing shop drawing submissions for dimensional and detail compliance
  • Evaluating "or equal" substitutions against original specification requirements
  • Checking certification and testing data against spec-required standards
  • Documenting compliance decisions in the submittal log for future reference
  • Expediting review cycles when multiple submittals require rapid turnaround

Data Sources

  • submittal_log — Historical record of submitted items, spec sections, review dates, and recommendation status
  • spec_sections — Structured project specifications with required fields:
    • submittal_required (boolean) — indicates if spec section requires submittal review
    • key_req (array) — critical requirements in natural language
    • tolerances (object) — dimensional and performance tolerances
    • testing (array) — ASTM, ASHRAE, or other standards for verification
    • environmental (object) — VOC, lead-free, sustainability requirements
    • divisions (CSI division codes) — Division 03, 05, 07, 08, 09, etc.
  • key_materials — Material specifications database with properties, certifications, and approved equal products
  • document-intelligence skill — Used to parse and extract data from submittal PDFs, data sheets, and shop drawings
  • project-data skill — Used to retrieve and reference project-specific requirements and approved materials

Workflow

1. Identify the Submittal

  • Retrieve submittal ID from submittal_log if resubmission
  • Or accept new submittal document (PDF, image, data sheet)
  • Extract cover letter, item description, and submission metadata

2. Determine the Spec Section

  • Query submittal_log by submittal ID to find associated CSI spec section
  • If new submittal, ask user to specify relevant spec section (e.g., "Division 03 Concrete", "Division 08 Doors and Frames")
  • Confirm with user if ambiguous

3. Load Spec Requirements

  • Retrieve spec section from project intelligence
  • Extract all relevant requirements into a structured checklist:
    • Material properties (grade, PSI, finish, color)
    • Dimensional tolerances (sizes, clearances)
    • Performance ratings (fire ratings, sound ratings, load capacity)
    • Testing standards (ASTM references with specific test methods)
    • Environmental compliance (VOC limits, lead-free, RoHS)
    • Certifications (UL, ICC, NFRC, FINEGRAIN, etc.)
  • Note any "or equal" or "approved equal" clauses that allow substitutions

4. Parse Submittal Document

  • Use document-intelligence skill to extract:
    • Product name, model, manufacturer
    • Technical specifications and properties
    • Dimensional data (from shop drawings or product data)
    • Testing certifications and lab reports
    • Material certifications and safety data
    • Installation notes and conditions
  • Organize extracted data in same format as spec requirements for direct comparison

5. Build Compliance Matrix

  • Create line-by-line comparison table:
    • Column 1: Spec Requirement (reference code, e.g., "03.03.01")
    • Column 2: Requirement Text (extract from spec)
    • Column 3: Submitted Value (extract from submittal document)
    • Column 4: Compliance Status (Compliant / Non-Compliant / Partially Compliant / Unable to Verify)
    • Column 5: Notes (explanation or citation)
  • Sort by compliance status to highlight non-compliances first

5a. Auto-Populated Compliance Matrix

When /process-docs processes a submittal package, the compliance matrix should be auto-populated before the user runs /submittal-review:

  1. From the submittal package, extract all product specifications (model, performance values, certifications, test reports)
  2. From specs-quality.json, load the relevant spec section requirements for the material type
  3. For each spec requirement, find the corresponding submitted value:
    • Match by property name (e.g., "compressive strength" in spec → "f'c" in submittal)
    • Match by ASTM standard (e.g., spec requires "per ASTM C39" → look for C39 test results)
    • Match by performance category (e.g., "fire rating" in spec → "UL listing" in submittal)
  4. Pre-populate the compliance matrix:
    | Spec Requirement | Required Value | Submitted Value | Compliance | Source |
    |---|---|---|---|---|
    | Compressive strength | ≥4,000 PSI | 4,500 PSI | ✅ PASS | Mix design report p.2 |
    | w/c ratio | ≤0.45 | 0.42 | ✅ PASS | Mix design report p.3 |
    | Air content | 5-7% | Not provided | ❓ MISSING | — |
    
  5. Flag any row where:
    • Submitted value < required value → FAIL
    • Submitted value is missing → MISSING DATA
    • Submitted value can't be compared (different units, different test standard) → NEEDS MANUAL REVIEW

This auto-population happens during /process-docs extraction. The /submittal-review command then presents the pre-filled matrix for the superintendent to confirm, override, or supplement with field observations.

6. Determine Compliance Status

  • Compliant — Submitted value exactly matches or exceeds spec requirement
  • Non-Compliant — Submitted value falls short of spec requirement (cite specific deficiency)
  • Partially Compliant — Submittal addresses requirement in part but leaves ambiguities or conditions
  • Unable to Verify — Required specification data missing from submittal (request clarification)
  • See compliance-checking.md for detailed determination rules and examples

6a. Concrete Mix Design Submittal Review

When reviewing concrete mix design submittals, refer to the concrete-mix-design-extraction template in the foremanos-intel plugin's document-intelligence skill for detailed extraction guidance (if installed). Key compliance checks:

  • Design f'c meets or exceeds specified f'c (with appropriate overdesign margin)
  • w/c ratio does not exceed specified maximum
  • Air content within specified range (especially for freeze-thaw exposure)
  • Cement type matches spec requirement (Type I, II, III, V)
  • Aggregate meets gradation and maximum size requirements
  • Admixtures are from approved manufacturers list (if specified)
  • Lab performing trial batch is accredited
  • Cold weather and hot weather modification plans are included if project has temperature-dependent specs

7. Generate Overall Recommendation

Synthesize compliance matrix into recommendation:

  • Approved — All requirements met, no deviations or exceptions. Ready for installation/procurement.
  • Approved as Noted — All critical requirements met; minor clarifications, conditions, or non-critical deviations noted. Approved with contingencies documented.
  • Revise and Resubmit — Specific deficiencies identified. Contractor must address identified items and resubmit. Cite section references and required corrections.
  • Rejected — Does not meet fundamental spec requirements. Resubmit with different product/approach or escalate for waiver consideration.

8. Draft Review Comments

  • Write in professional, objective tone suitable for RFI response or meeting minutes
  • Use structured comment format: [Status] | [Spec Reference] | [Finding] | [Required Action]
  • Group comments by spec section or compliance status
  • Include recommendations for follow-up (additional testing, certification, shop drawings, etc.)
  • Cite all references to spec sections, ASTM standards, test reports
  • For non-compliances, specify corrective action required

9. Update Submittal Log

  • Record review date, reviewer, recommendation, and comments
  • Link to compliance matrix and any supporting documents
  • If resubmission, note previous revision status and what changed
  • Flag for escalation if needed (structural engineer, code official, etc.)

Review Comment Language Standards

Approved

The submitted [product/material] meets all applicable specification requirements and is approved for [procurement/installation].

Approved as Noted

The submitted [product/material] meets specification requirements subject to the following conditions/clarifications:

  • [Condition 1]: [explanation, deadline, or required action]
  • Approval granted pending completion of noted items.

Revise and Resubmit

The submitted [product/material] does not meet specification in the following respects:

  • [Reference code] [Requirement]: Specification requires [required value]. Submittal provides [submitted value]. [Specific corrective action required].
  • [Reference code] [Requirement]: ... Please resubmit with corrections or request formal waiver if waiver is intended.

Rejected

The submitted [product/material] is not acceptable due to non-compliance with fundamental specification requirements:

  • [Critical deficiency 1]
  • [Critical deficiency 2] Resubmit with alternative product meeting all spec requirements, or submit formal waiver request for architect/engineer consideration.

Lead-Time Alert System

The submittal-intelligence skill tracks submittal timelines and flags items at risk of missing critical path deadlines. This system prevents procurement delays, schedule impacts, and last-minute rush approvals.

Must-Submit-By Calculation

Working backwards from each submittal's critical path impact:

Timeline Logic:

  1. Activity Start Date (from schedule.json → activities linked to this submittal)
  2. Minus Material Lead Time (from procurement specs or supplier standard terms)
  3. Minus Fabrication Time (manufacturer lead time after order placed; typically 2-8 weeks)
  4. Minus Approval Cycle Time (architect/engineer review to approval):
    • Standard products (common, pre-approved): 2-4 weeks
    • Complex/custom products (engineered, mock-ups, samples): 4-6 weeks
  5. Minus Preparation Time (contractor prep of drawings, samples, certifications): 1-2 weeks

Example Calculation:

Activity start date (PEMB erection): 03/23/2026
Minus: PEMB lead time: 30 days
Minus: Fabrication time: Already in PEMB lead time, covered
Minus: Approval cycle (engineered): 4 weeks
Minus: Preparation (drawings ready): 1 week
───────────────────────────────────
Must-submit-by date: 02/02/2026

Alert Tiers

Three escalating alert levels based on days remaining until must-submit-by date:

Tier Days Remaining Status Action
CRITICAL Past due (negative) Red flag Submittal missed deadline. Escalate to PM/engineer immediately. Assess schedule impact. May require expedited review or change order.
WARNING 0-7 days Yellow flag Due within one week. Verify submittal ready for submission. Confirm with architect review slot reserved. Prepare expedited review package if needed.
WATCH 8-21 days Blue flag Due within 3 weeks. Monitor preparation progress. Confirm no blockers (missing data, approvals, samples). Schedule architect review.
NORMAL >21 days Green On track. No action needed. Continue normal schedule.

Daily Morning-Brief Auto-Check

The /morning-brief command automatically scans submittal-log.json and generates an alert summary:

Query logic:

  • Find all submittals with status != "approved"
  • Calculate must-submit-by date working backwards from linked schedule activities
  • Compare to today's date
  • Generate alert for each tier

Morning Brief Output Example:

SUBMITTAL STATUS — ALERTS ONLY (3 items at risk)

🔴 CRITICAL — Past Due
  • Nucor PEMB Reaction Drawing (SUB-008)
    Status: "under_review" (submitted 02/09, 9 days ago)
    Needed by: 02/02 (7 DAYS PAST DUE)
    Impact: PEMB erection critical path blocked
    Action: Call Nucor today; escalate to CMW architect

🟡 WARNING — Due in 3 Days
  • Schiller Door Hardware (SUB-012)
    Status: "revision_submitted" (resubmit 02/15)
    Needed by: 02/18 (3 days)
    Impact: Door procurement dependent
    Action: Confirm with architect; hold time slot for review

🔵 WATCH — Due in 18 Days
  • Davis & Plomin HVAC Equipment (SUB-015)
    Status: "under_review" (submitted 02/10)
    Needed by: 03/05 (18 days)
    Impact: HVAC procurement, MEP rough-in scheduled 04/27
    Action: No urgent action; normal tracking

Project Intelligence Integration

When reviewing submittals or generating alerts, automatically enrich with data from the project intelligence store. These cross-references improve review accuracy and catch procurement/schedule risks early.

Procurement Lead Time Enrichment

Read procurement-log.json → For each submittal, look up the corresponding procurement entry by submittal_id. Pull expected_delivery, lead_time_weeks, and delivery_status → auto-populate fabrication_days and material_lead_time_days in the submittal record. If procurement entry shows delivery_status = "delayed", escalate the submittal alert tier accordingly.

Sub Contact Resolution

Read directory.json → subcontractors[] → When a submittal is overdue or needs follow-up, resolve the responsible sub's foreman name, phone, and email from the directory. Auto-fill contact information in alert action items: "Contact {foreman} at {phone} ({sub_name}) to expedite SUB-{id}."

Inspection Hold Point Linking

Read specs-quality.json → hold_points[] → For each submittal's spec_section, check if any hold points require submittal approval before the inspection can proceed. Flag linked hold points: "SUB-{id} approval is a prerequisite for hold point HP-{hp_id} ({inspection_name}). Inspection cannot proceed until this submittal is approved."

Cost Impact Flagging

Read cost-data.json → For submittals linked to critical path activities or high-value budget line items, show the budget amount at risk if approval is delayed. Include in alert output: "Budget line item {division} — {description}: ${amount} at risk if SUB-{id} delays procurement by {N} days."

Quality Test Correlation

Read quality-data.json → After a submittal is approved (status = "approved"), link subsequent material test results back to the approved submittal. For example, an approved concrete mix design (SUB-XXX) should be cross-referenced when 7-day and 28-day break results arrive: "Break test results for {mix_id} — 28-day f'c = {value} PSI vs. approved design f'c = {design_value} PSI. Status: {pass/fail}."

Installation Verification

Read daily-report-data.json → Flag if materials from a submittal are documented as installed in a daily report before the submittal status = "approved": "WARNING: {material} from SUB-{id} appears installed per daily report #{report_number} on {date}, but submittal status is still '{status}'. Verify approval before installation proceeds."

Submittal-Log Data Structure

For lead-time tracking, each submittal in submittal-log.json must include:

{
  "id": "SUB-008",
  "item": "PEMB Reaction Drawing",
  "spec_section": "05 42 00",
  "submitting_sub": "Alexander Construction / Nucor",
  "status": "under_review",
  "submitted_date": "2026-02-09",
  "must_submit_by_date": "2026-02-02",
  "approval_cycle_days": 4,
  "material_lead_time_days": 30,
  "fabrication_days": 0,
  "preparation_days": 7,
  "linked_schedule_activity_id": "A45-PEMB-Erection",
  "linked_activity_start_date": "2026-03-23",
  "critical_path_blocked": true,
  "days_past_due": 7,
  "alert_tier": "CRITICAL",
  "notes": "Nucor sent initial, needs revisions for anchor bolt details"
}

Rejection/Resubmission Workflow

When a submittal is rejected or returned for revisions, auto-calculate new timeline impact:

Trigger: Submittal status changes from "under_review" to "revise_and_resubmit" or "rejected"

Auto-Calculation:

  1. Set new revision_number (increment from previous)
  2. Capture original must_submit_by_date
  3. Record rejection_reason from architect's comments
  4. Estimate resubmission time (typically 3-5 business days for major revisions, 1-2 for minor)
  5. Add resubmission lead time to today to get new expected_resubmit_date
  6. Recalculate new must_submit_by_date (if 2nd revision, time is even tighter)
  7. Compare new deadline to original; flag if slipping past must-submit-by
  8. Alert to PM: "Resubmission due [date]. New approval cycle leaves [N] day margin."

Example Rejection Timeline:

SUB-008 PEMB Reaction Drawing (Nucor)
Original submission: 02/09
Original must-submit-by: 02/02 (MISSED by 7 days)
Rejection date: 02/12
Rejection reason: "Anchor bolt embedment depth needs verification per geotechnical report"
Estimated resubmission: 02/15 (3 days for revisions)
New approval cycle: 4 days (expedited given past-due status)
New must-submit-by: 02/19 (16 days past original deadline!)
Action: Flag to PM; assess schedule impact; consider change order if erection delayed

Resubmission Tracking

Track each revision with separate entries to maintain history:

In submittal-log.json:

{
  "id": "SUB-008",
  "item": "PEMB Reaction Drawing",
  "revision_history": [
    {
      "revision_number": 1,
      "submitted_date": "2026-02-09",
      "status": "revise_and_resubmit",
      "rejection_reason": "Anchor bolt embedment depth needs verification per geotechnical report",
      "rejection_date": "2026-02-12",
      "approval_cycle_days": 4,
      "must_submit_by_date": "2026-02-02",
      "days_late": 7
    },
    {
      "revision_number": 2,
      "submitted_date": "2026-02-15",
      "expected_approval_date": "2026-02-19",
      "status": "under_review",
      "approval_cycle_days": 4,
      "must_submit_by_date": "2026-02-19",
      "days_late": 17,
      "turnaround_time_days": 3,
      "notes": "Expedited review requested; geotechnical verification confirmed"
    }
  ],
  "current_revision_number": 2,
  "total_revisions": 2
}

Critical Path Submittal Flagging

Cross-reference each submittal with schedule.json critical path to flag items that will block the schedule if delayed:

Linking logic:

  • Submittal's spec_section maps to schedule.json material requirement
  • Check if linked activity has float = 0 or < 5 days
  • If yes, set critical_path_blocked = true
  • These submittals get priority flagging in alerts

Example:

SUB-008 PEMB Reaction Drawing
  Linked activity: A45-PEMB-Erection (critical path)
  Float: 0 days
  Flag: CRITICAL_PATH_BLOCKED = true
  Alert priority: Highest — any delay impacts substantial completion

SUB-015 HVAC Equipment Data
  Linked activity: A72-MEP-Rough-In (near-critical, float = 5)
  Float: 5 days
  Flag: CRITICAL_PATH_BLOCKED = false (but near-critical)
  Alert priority: Medium — some schedule cushion but tight

Integration with /morning-brief and /daily-report

Morning Brief (/morning-brief):

  • Scan all submittals with status != "approved"
  • List only CRITICAL and WARNING tiers (skip WATCH/NORMAL unless requested)
  • Include must-submit-by dates and linked activities
  • Provide action items for each flagged item

Daily Report (/daily-report):

  • Include new rejections or resubmissions in "Open Items" section
  • Note any submittals that crossed into CRITICAL or WARNING during the day
  • Track turnaround time for resubmissions (days between rejection and resubmit)
  • Update schedule impact assessment if critical path activities are affected

Cross-References

  • project-data skill — Retrieves project-specific spec sections, approved materials, and submittal requirements
  • document-intelligence skill — Parses PDFs and extracts structured data from submittal documents, data sheets, test reports, and shop drawings
  • spec-requirement-extraction.md — Detailed guidance on identifying and structuring testable requirements from CSI specs
  • compliance-checking.md — Detailed determination rules, evaluation methodology, and review comment templates