Purpose
The immission control permit procedure is the central intervention and control interface for industrial installations. A permit is effective only if formal requirements (correct procedure, public participation, concentration of authorities under § 13 BImSchG) and substantive requirements (§ 5 BImSchG: protection, precaution, waste avoidance and energy efficiency obligations) are met. This skill reviews both and classifies third-party protection, neighbour actions and association actions.
Inputs
- Installation type and location (federal state, outdoor/indoor area, protected areas)
- Intended activity and capacity (quantities, output, number of animals)
- Existing decision or application (if available)
- Neighbourhood (residential development, SAC/bird protection area, water protection area)
- Urban land-use planning at the site (B-plan, F-plan, § 35 BauGB)
Sub-agent architecture
Researcher provides the 4th BImSchV installation number, relevant TA rule sets, Federal Administrative Court and CJEU case law. Drafter prepares the expert opinion in the order formal → substantive → third-party protection and reviews the operative provisions. Reviewer reviews EU conformity (IED 2010/75/EU), protected area affectedness and action deadlines.
Procedure
1. Permit requirement under § 4 BImSchG in conjunction with the 4th BImSchV
| Step | Review |
|---|---|
| Installation catalogue | Subsumption under Annex 1 to the 4th BImSchV. Column c) or d) determines the procedure |
| Quantity thresholds | Installations below the threshold: not subject to a permit, fall under §§ 22 et seq. BImSchG (operator obligations) |
| Construction threshold vs. modification permit | § 16 BImSchG: a substantial modification requires its own permit |
2. Choice of procedure
| Procedure | Norm | Consequence |
|---|---|---|
| Formal | § 10 BImSchG in conjunction with 9th BImSchV | Public participation, discussion meeting, EIA integration § 4 UVPG |
| Simplified | § 19 BImSchG | Without public participation – only for column c) installations |
| Notification § 15 BImSchG | Non-substantial modification | No permit, only notification |
Standard for procedural defects: Federal Administrative Court, judgment of 22 October 2015 – 7 C 15/13, NVwZ 2016, 308 [unverifiziert – prüfen]; CJEU, judgment of 15 October 2015 – C-137/14 (Commission v. Germany) – material preclusion incompatible with EU law.
3. Substantive permit requirements § 5 BImSchG
| Obligation | Norm | Content |
|---|---|---|
| Protection obligation | § 5 (1) no. 1 BImSchG | No harmful environmental impacts (TA Luft, TA Lärm); third-party protective |
| precautionary duty | § 5(1) no. 2 BImSchG | state of the art (§ 3(6) BImSchG), BAT conclusions IED; not third-party protective (prevailing view, dissenting in part Jarass) |
| waste avoidance | § 5(1) no. 3 BImSchG | recovery, otherwise disposal |
| energy efficiency | § 5(1) no. 4 BImSchG | efficient energy use |
4. Conditions and ancillary provisions § 12 BImSchG
- Definiteness § 37 VwVfG (clearly definable act/sufferance/omission)
- Proportionality (suitable, necessary, appropriate)
- Distinguish modifying condition vs. subsequent order § 17 BImSchG
- Security § 12(1) BImSchG, insofar as recultivation/decommissioning obligation
5. Third-party protection and legal protection
| Claimant | Basis |
|---|---|
| Neighbour | Action against permit, based on third-party protective norms (§ 5(1) no. 1 BImSchG, if applicable § 15 BauNVO duty of consideration) |
| Recognised environmental association | § 2 UmwRG, extended to procedural errors under § 4 UmwRG |
| Project developer | Obligation action for grant; action for failure to act § 75 VwGO |
6. Subsequent order and decommissioning
- § 17 BImSchG – subsequent order for subsequently recognised risks or changed requirements (state of the art)
- § 20 BImSchG – prohibition of operation, decommissioning, removal; hearing § 28 VwVfG mandatory
- § 21 BImSchG – revocation
Sources and citation style
Binding: ../../../references/zitierweise.md.
Statutes / Ordinances
- §§ 4–7 BImSchG (permit)
- § 5 BImSchG (substantive requirements)
- § 10 BImSchG (public participation)
- § 12 BImSchG (conditions)
- § 13 BImSchG (concentration effect)
- § 17 BImSchG (subsequent order)
- § 20 BImSchG (decommissioning)
- §§ 22 ff. BImSchG (installations not requiring a permit)
- 4. BImSchV (installation catalogue)
- 9. BImSchV (procedure ordinance)
- TA Luft 2021
- TA Lärm 1998
- IED 2010/75/EU
Commentaries
- Jarass, BImSchG, 14th ed. 2022, § 4 marginal no. 1 ff., § 5 marginal no. 1 ff., § 10 marginal no. 1 ff.
- Dietlein, in: Landmann/Rohmer, Umweltrecht (loose-leaf, as of: 2024), § 5 BImSchG marginal no. 50 ff.
- Hansmann/Röckinghausen, in: Landmann/Rohmer, § 10 BImSchG marginal no. 100 et seq. (public participation)
- Storost, in: Landmann/Rohmer, § 17 BImSchG marginal no. 30 et seq. (subsequent order)
Case law ([unverifiziert – prüfen in Beck-Online/juris/BVerwG-Datenbank])
- Federal Administrative Court, judgment of 22.10.2015 – 7 C 15/13, NVwZ 2016, 308 (state of the art)
[unverifiziert – prüfen] - Federal Administrative Court, judgment of 24.10.2013 – 7 C 36/11, BVerwGE 148, 155 (third-party protection under § 5 BImSchG)
[unverifiziert – prüfen] - Court of Justice of the European Union, judgment of 15.10.2015 – C-137/14, ECLI:EU:C:2015:683 (substantive preclusion / EIA Directive)
[unverifiziert – prüfen] - Federal Administrative Court, judgment of 21.11.2018 – 7 C 17/16, NVwZ 2019, 567 (association action / § 4 UmwRG)
[unverifiziert – prüfen]
Output format
GUTACHTEN — Immissionsschutzrechtliche Genehmigung
<Mandat-Kürzel> — <Datum>
I. Sachverhalt
Anlage: <Typ, Kapazität, Standort>
Vorhaben: <Errichtung / Änderung / Anzeige>
Umgebung: <Wohnbebauung, Schutzgebiete>
II. Frage(n)
1. Ist die Anlage genehmigungsbedürftig?
2. Welches Verfahren ist einschlägig?
3. Liegen die materiellen Voraussetzungen § 5 BImSchG vor?
4. Welche Drittschutz-/Verbandsklagerisiken bestehen?
III. Kurzantwort
<ein Satz>
IV. Rechtliche Bewertung (Gutachtenstil)
1. Genehmigungsbedürftigkeit § 4 BImSchG i. V. m. 4. BImSchV
- Anlagennummer: <Anhang 1 Nr. …>
- Spalte c) / d)
2. Verfahren
- § 10 BImSchG / § 19 BImSchG
- Öffentlichkeitsbeteiligung 9. BImSchV
- UVP-Integration § 4 UVPG (Verweis auf uvp-verfahrenspruefung)
3. Materielle Voraussetzungen § 5 BImSchG
a) Schutzpflicht — TA Luft / TA Lärm
b) Vorsorgepflicht — Stand der Technik / BVT
c) Abfallvermeidung
d) Energieeffizienz
4. Auflagen § 12 BImSchG
- Bestimmtheit, Verhältnismäßigkeit
5. Drittschutz und Verbandsklage
- Nachbarklage (drittschützende Normen)
- § 2 UmwRG / § 4 UmwRG
V. Gesamtergebnis
<…>
VI. Risiken / offene Punkte
- Emissionsprognose ausstehend
- FFH-Vorprüfung erforderlich?
- Schallgutachten (TA Lärm) aktualisieren
VII. Risikoeinstufung
[🟢 / 🟡 / 🔴]
VIII. Quellenverzeichnis
<gem. zitierweise.md>
Risks / typical errors
- Wrong installation number in the 4th BImSchV → wrong procedure, formal unlawfulness.
- Simplified procedure instead of formal procedure → association action succeeds under § 4 UmwRG because public participation is lacking.
- Precautionary duty confused with protective duty → third-party protection wrongly affirmed/denied.
- Conditions indeterminate (§ 37 VwVfG) → individual ancillary provisions can be challenged, the main permit does not necessarily waver, but enforcement fails.
- State of the art outdated → precautionary duty breached, subsequent order under § 17 BImSchG looms.
- FFH compatibility / species protection overlooked → not the subject of the skill in the narrower sense, but the permit fails under § 34/§ 44 BNatSchG.